2019-02-27 Retrospective

Date
Team Anand, Ayub, Kartheek, Anil, Mahesh, Chitranshu, Asha, Vinaya,
Participants

Background

Retrospective

Start doingStop doingKeep doing
  • Chitranshu has helped with work planning,tracking sheet that has helped to track the team and work usage. Can be shared with other team folks.
  • Rotation of people within team gives and opportunity to work on other technologies, reduce dependency during their unavailable times and team members are happy with that
  • Start of the sprint, stories are marked 'Selected for Development' by mobile team and has been helpful to track any scope change.
  • use of slack bot for standup has been helpful to track team's (content framework) updates
  • Stories that had complete clarity only was taken up by KP team and any stories that came in between and needed more clarity was moved out to next sprint. Was communicated to PMs earlier on through Jira ticket comments
  • Status updates on Jira must happen more regularly
  • The single scrum board has helped else creating individual filters was hard
  • Deployment script post code freeze must be available DevOps instead of creating just before PROD deployment as this led to some of the tasks missed (forgotten)
  • Retrospective if had earlier would be beneficial as you tend to remember points then
  • Process changes related to bugs from QA, Implementation team must be prioritised by PMs that needs to be resolved
  • Communication on process changes must be discussed by TMs
  • Jira simplification must be done especially status change workflows
  • Sprint 3 code ended up in pre-prod. Find the root cause and take action accordingly
  • Timeboxing developers with release timeline or calendar without buffers is hampering creativity and productivity of team folks and there should be time given to nurture them as these ideas will flow into features/implementation that they are building. Ex: Google has one day a week as creativity day 
  • Teams must be trusted as team members are working hard on whatever has been assigned
  • Low level team members are not accountable and they rely upon managers for every thing
  • Developers must be able to analyse and understand his/her change  how does it fits in the big picture and be responsible for end to end delivery
  • Feedback to developers must be given , that is not the culture (Top-Down) here and this is adding burden on the Tech Mgrs as they are held accountable.
  • Bottom up culture could be good 
  • Showcase is preferable to be done between PMs and team members for a given epic and relevant stakeholders
  • Timeline/Release delays must be communicated to all the stakeholders which is currently not happening
  • Release delays must have scope reviewed and published if the release has to happen on the given date
  • Go/No-Go  Calls for pre-prod with TMs, PMs must be made for a PROD release 
  • When number of issues are high, there has to be a meeting with all stakeholders to arrive at a decision on what will be taken up and get an ETA for the same
  • During the planning week QA is busy with stage validation which leaves with no time for participation in the planning
  • Showcase must be planned for Monday
  • Release week - extra time for exploring required as it was earlier ( 1 week between sprints/release). This is from Tech Managers and Tech Leads point of view.
  • Labels on UX needs to be consistent for DEV and QA else is raising bugs which are invalid
  • Can mobile build have a separate build plan/cycle as they need to provide the build only after the product build goes to staging?
  • Jira fields if they can have intelligent defaults, that will be save time and will be helpful
  • Scope change is a concern, can there be a static filter ?
  • Code freeze on Thursday and Showcase on Friday
  • Dependency management instead of google sheets, can it happen through Jira ?
  • Spread sheet for variables tracker is not a right away to manage
  • Atleast read access to repos must be provided by DevOps to validate the variables. DevOps has missed most of the time and this has caused issues in Pre-PROD and PROD
  • KP gets interrupts directly from field which eats up team bandwidth and this should be streamlined
  • Putting pressure on team for continuous delivery is hard
  • Centralising showcase is not effective as not all scenarios can demoed in the interest of time and it does not seem beneficial
  • If PMs are not there in showcases then the effectiveness is lost
  • Timelines on QA has been pushed upon and no inputs has been taken up for revising timelines
  • Adhoc task for QA like android testing, 1 MBPS etc. QA needs prioritisation too to be able to quality deliver
  • The time crunch is hampering testing innovation
  • DevOps lapses, env down time but still QA is expected to complete on time
  • PMs must not bypass Project Managers for any new work coming into QA
  • Continue using the planning/tracking sheet
  • Continue rotation of team members
  • Continue tagging stories with 'Selected for Development' which are sprint ready
  • wil continue using the bot for standup updates
  • Sprint 1 had sufficient time to plan 