Priority | Item | Effort (Approx) | Timeline |
---|---|---|---|
P0 |
| 4 Hrs | April 12 |
P1 |
| 6-8 Hrs 16 Hrs | April 17 April 24 |
P2 |
| 10 Hrs | April 27 |
P3 |
| 2 Hrs 4 Hrs 8 Hrs | April 28 April 28 May 3 |
P4 |
| 12 Hrs | May 6 |
- Grafana & Prometheus - CQ429 & CQ444
- Automatic upgrades - Functionality is available
- Scaling of NiFi : PoC & Estimation - CQ451 - 16-20Hrs
- PoC - 8-12 Hrs
- Flow & UAC - 2Hrs
- LLD - 4Hrs
- Estimation - 2Hrs
- Login Role based access Roles - CQ371 - AUTHORIZATION objects (P1), SSO with role awareness ( Role → Authentication → Access) - 10 Hrs
- Flow & UAC - 2Hrs
- LLD - 4Hrs
- Estimation - 4 Hrs (Need to get input from team)
- Drill Down Report - 10Hrs - P2 (State Officer Level for 1st Phase)
- Flow & UAC - 2Hrs
- LLD - 4 Hrs
- Estimation - 4 Hrs (Need to get input from team)
- Dimension Problem
- Validate Event Data with Dimension
- Source of Dimension
- Document with all options & pros - 4 Hrs - P0
- Making Specs Public
- Putting the JSON in the document - 2Hrs - P3
- Document on creating a new program, indicators
- Document with steps - 4Hrs - P3
- Upgradation : How can we plan
- Full Re install (Right now following)
- Delta upgrade (From 5.0 onwards) - 12Hrs - P4
- Discussion with DevOps team - 1 Hr
- Flow & UAC - 4 Hrs
- LLD - 4Hrs
- Estimation - 2 Hrs
- KeyCloak Bulk Users: - P3
- Partial Import + Verify email (Email Id should given)
- REST APIs and a program (Email/Sms) - Need to consider this option - 8 Hr
- Functional Flows & UAC - 4 Hrs
- LLD - 2 Hrs
- Estimation - 2 Hrs
- Allow self registration - Should not be enabled
- IFTTT Nudges powered by UCI - 16 Hrs - P1
- Understanding requirements - 4 Hrs
- Functional Flows & UAC - 4 Hrs
- HLD - 2 Hrs
- LLD - 4 Hrs
- Estimation - 2 Hrs
Need to be considered later
Test Automation Strategy